Webber lands $538M Fort Worth reclamation plant, Ferrovial's biggest US water job

Ferrovial's Texas contractor Webber will build the greenfield Mary's Creek Water Reclamation Facility in west Fort Worth. Work starts this month and runs to summer 2030.

QP Group · 15 Nov 2026 · 2 min read · From The Civil Brief Vol. 4

Ten million gallons a day, from a plant that doesn't exist yet. Webber, the Ferrovial subsidiary based in The Woodlands, Texas, has won the contract to build Fort Worth's new Mary's Creek Water Reclamation Facility, Construction Dive reported on 13 November. The contract is worth $537.9 million, and it's described as Ferrovial's largest water infrastructure project in the US to date.

What gets built

Mary's Creek is a greenfield site. Webber's scope covers the wastewater treatment systems, solids handling and odor control, along with the electrical, instrumentation and control systems that tie the plant together.

Get The Civil Brief every TuesdayThree-minute read. Free. One-click unsubscribe.

The plant has two jobs. It adds wastewater capacity on the west side of Fort Worth, and it produces reclaimed water for industrial users and irrigation. Once running, it will handle 10 million gallons a day. Construction is set to start in November 2026, with completion expected by summer 2030.

Webber's Texas water run

This isn't Webber's first big water win in the state. In December 2025 it picked up two jobs worth $721 million combined, per Construction Dive: a $426 million, 105-foot-deep pump station tied to TxDOT's I-35 Capital Express Central project in Austin, and a $295 million expansion of Fort Worth's Eagle Mountain Water Treatment Plant.

So in under a year Webber has stacked up more than $1.2 billion of Texas water and wastewater work, with Fort Worth as a repeat client.

Why Texas, why now

Peter Bailey, president of waterworks at Webber, summed up the demand drivers in one line:

"Population growth, industrial expansion and increasing pressure on existing water supplies" Peter Bailey, President of Waterworks, Webber

He also said he expects strong demand in the US water market over the next several years, particularly in the Southeast, where population projections point to continued need over the next five to ten years.

The money is there too. Texas lawmakers passed bills last year to put $20 billion into the state's water sector. And Dallas-Fort Worth is the only US metro with two cities of more than 1 million people, according to Fort Worth's economic development partnership, which also ranks Fort Worth among the fastest-growing large cities in the country.

The bigger picture

Treatment plants are a different build from roads and bridges. They run long, they're process-heavy, and the last year is mostly about electrical, controls and startup. A four-year greenfield plant in a growth market, backed by state water money, is exactly the kind of job that keeps a contractor's water division staffing up rather than shuffling people between sites.

What it means for hiring

  • Our read: a four-year greenfield plant needs a full site team for the long haul: project managers, process mechanical and E&I superintendents, and commissioning leads who have started up treatment plants before.
  • Contractors growing their water work in Texas are fishing in the same small pool of treatment-plant specialists. Experienced water superintendents in DFW and Austin should expect a lot of calls.
  • With $20B of state water funding in play, local leadership with Texas utility relationships becomes a real advantage when bidding the next wave of plants.

Building a team in Heavy Civil & Infrastructure?

Connor Goodall specialises in Heavy Civil & Infrastructure hiring at QP Group. Talk to Connor about the market, salaries or a search.

Sources

  1. Ferrovial wins $538M Texas water project · Construction Dive · 13 Nov 2026
  2. Ferrovial wins $721M in Texas water projects · Construction Dive · 3 Dec 2025

Written by QP Group from the reporting and announcements above. Figures and quotes belong to the original sources.

Connor Goodall
Connor GoodallSenior Consultant · Heavy Civil & Infrastructure
Get The Civil Brief every Tuesday →

Get The Civil Brief in your inbox

A three-minute weekly read: funding, launches, leadership moves and what they mean for hiring. From Connor Goodall. No spam, one-click unsubscribe.

Free, weekly. One-click unsubscribe anytime.