Two machines, each trailing roughly 500 feet of gantry, are now chewing through hard rock under North Bergen. The Gateway Development Commission said on 18 November that a second tunnel boring machine has started excavating the southern tube of the $16 billion Hudson Tunnel Project, so both new rail tubes are now under construction, ENR reported.
Where things stand
The northern machine started in October. It has moved about 400 feet and installed more than 60 precast concrete lining rings. The pair are driving parallel 5,100-foot tunnels through the Palisades, from the portal in North Bergen to the Hudson County Access Shaft on the Weehawken-Hoboken border. GDC expects that stretch to take about a year, including planned maintenance stops.
"Launching the second tunnel boring machine marks another significant step toward delivering the most urgent passenger rail infrastructure project in America." Tom Prendergast, CEO, Gateway Development Commission
The machines
Both are single-shield hard-rock machines with 28-foot, 8-inch cutterheads. Each will place nearly 850 lining rings built from more than 5,000 precast segments as it goes. Jim Starace, GDC's chief of program delivery, told the board that a small crane inside the shield lifts each segment into place and crews bolt them together, Construction Dive reported. The Palisades section also has six cross passages linking the two tubes.
Starace said the southern machine is still ramping up and that production should keep rising until both break through in Weehawken. At the far end, crews have dug the access shaft about 50 to 60 feet down and hit rock. He expects the shaft to be finished and the machines to break through around this time next year.
Who's doing the work
A joint venture of Schiavone Construction, Lane Construction and Dragados holds the Palisades Tunnel package, which covers the excavation and the access shaft. The Port Authority of New York and New Jersey is managing delivery with GDC.
What comes next
Once the first pair of machines reach the shaft, they come out and a second pair built for the mixed ground under the Hudson goes in. Starace said boring on the river section is slated to start in 2028. The new twin tubes will eventually sit alongside the existing North River Tunnel, which is lined up for rehabilitation under the Gateway Program.
That's a long, staged program with years of tunneling still ahead. For heavy civil firms in the region, it's a steady pull on underground specialists while the rest of the corridor keeps moving.
What it means for hiring
- Our read: hard-rock and soft-ground tunneling are different trades. The switch to mixed-ground machines in 2028 will need TBM operators, tunnel engineers and supers who have worked under water and in variable ground, a small pool in the US.
- Segment production and ring-build quality control get busy when two machines are placing thousands of segments. QA/QC leads and precast coordinators with tunnel experience will be in demand on this job.
- Shafts and cross passages are their own specialty. Engineers and supers experienced in ground support and mining-style excavation will be needed across the Palisades section.
Building a team in Heavy Civil & Infrastructure?
Connor Goodall specialises in Heavy Civil & Infrastructure hiring at QP Group. Talk to Connor about the market, salaries or a search.
Sources
- Gateway Hudson Tunnel Project Starts Excavation of Second Rail Tube · ENR · 18 Nov 2026
- $16B Hudson Tunnel project launches second tunnel boring machine · Construction Dive · 19 Nov 2026
Written by QP Group from the reporting and announcements above. Figures and quotes belong to the original sources.

More from The Civil Brief
- Granite closes two materials deals, adding Utah quarries and Tennessee asphalt plants22 Nov 2026
- AECOM's backlog hits a record $28B, and it says IIJA money is mostly unspent22 Nov 2026
- Joseph B. Fay wins $38.6M job to clear the rest of Baltimore's Key Bridge22 Nov 2026
- Skanska and Traylor finish the $1.6B Portal North Bridge over the Hackensack22 Nov 2026