Maryland's Key Bridge rebuild has its first award under the new four-contract plan, and it came in below the agency's own estimate. The Maryland Transportation Authority board approved a $38.6 million demolition and miscellaneous marine work contract to Joseph B. Fay Co. on Thursday 19 November, MDTA said. Back in May, MDTA had put this package at $50 million to $100 million, per Construction Dive.
Fay is based in Pittsburgh and operates as part of S&B USA Construction. It isn't new to Baltimore: it was recently part of a joint venture with Skanska on CSX's Howard Street Tunnel.
What's in the job
The land-based remains of the old bridge are already gone. Crews finished removing them in February, including more than 20,000 tons of concrete decking and columns. Fay's work is the over-water part:
- removing and salvaging the remaining three-span steel girder sections over the Patapsco, near each riverbank
- demolishing eight marine piers and the two remaining land piers, one on each side of the river
- taking nine marine foundations down to the mud line
- cleaning out 96-inch-diameter steel pipe piles so concrete can be poured for the new bridge
MDTA invited proposals in August, took bids at the end of October and gave the work to the lowest-priced qualified bidder. It expects the work to start later this fall.
The four-contract plan
MDTA split the rebuild into four packages this year, saying it expected more competition, more chances for the local workforce and faster awards. Together they are estimated at $4 billion to $4.8 billion, Construction Dive reported.
Next up is the South Land Approach, a design-bid-build job with about 3,000 feet of approach bridge over land and ground improvements over wetland, estimated at $300 million to $400 million. MDTA plans to advertise it in late fall 2026 or early winter 2027, with construction starting in spring 2027. The North Land Approach, at $200 million to $300 million, advertises in winter 2027.
The big one is the main span: a design-build contract of up to $4 billion for a 3,365-foot cable-stayed bridge with a 1,665-foot main span and at least 230 feet of clearance over the channel, ENR reported in July. MDTA aims to pick a team in summer 2027 and is still working toward opening the new bridge to traffic by 2030.
The bigger picture
Splitting a megaproject into smaller packages lets mid-sized and regional contractors compete for work that would otherwise go to a handful of national JVs. The first result is a regional contractor winning on price. With two approach contracts still to bid in the next year or so, Mid-Atlantic bridge contractors have plenty to chase.
What it means for hiring
- Our read: marine demolition and pile work on a live shipping channel needs supers, marine equipment managers and engineers who have worked off barges and trestles. That pool is small, and Fay's mobilization will draw on it.
- Two land-approach contracts worth a combined $500 million to $700 million will bid over the next year. Expect regional bridge contractors to staff up their estimating and precon teams for them.
- The main span's 2027 selection means design-build teams will hold key people in place through the shortlist stage, which tightens supply of senior bridge PMs in the region.
Building a team in Heavy Civil & Infrastructure?
Connor Goodall specialises in Heavy Civil & Infrastructure hiring at QP Group. Talk to Connor about the market, salaries or a search.
Sources
- Maryland Transportation Authority awards Key Bridge rebuild marine work and demolition contract · Maryland Transportation Authority · 19 Nov 2026
- Punch List: Maryland awards demo contract on $4B Key Bridge rebuild · Construction Dive · 20 Nov 2026
- Maryland unveils 4 Key Bridge contracts totaling over $4B · Construction Dive · 20 May 2026
- Maryland Issues RFQ for Main Span of Key Bridge Rebuild · ENR · 21 Jul 2026
Written by QP Group from the reporting and announcements above. Figures and quotes belong to the original sources.

More from The Civil Brief
- Granite closes two materials deals, adding Utah quarries and Tennessee asphalt plants22 Nov 2026
- AECOM's backlog hits a record $28B, and it says IIJA money is mostly unspent22 Nov 2026
- Both Hudson Tunnel tubes are now being bored through the Palisades22 Nov 2026
- Skanska and Traylor finish the $1.6B Portal North Bridge over the Hackensack22 Nov 2026