The old Portal Bridge had a habit of getting stuck open. As of this month it doesn't matter. A Skanska and Traylor Bros. joint venture has delivered the $1.6 billion Portal North Bridge over the Hackensack River in New Jersey, and both tracks are now in full service, Amtrak said on Monday 16 November, when Gov. Mikie Sherrill joined NJ Transit and Amtrak officials in Kearny to mark the completion. Regular NJ Transit weekend service resumed on Sunday 15 November and weekday service the next day, the release said. Construction Dive has the build details.
What got built
The replacement is a 2.44-mile, two-track fixed span that sits 50 feet above the river, so it no longer has to open for boats. The swing bridge it replaces was 116 years old, and its tendency to jam open caused delays that rippled down the corridor for NJ Transit and Amtrak riders. It is due to be dismantled in 2027.
Getting there took two cutovers. The first track moved onto the new bridge between 13 February and 15 March; work on the second ran from 9 October to 16 November, a five-week squeeze on service between Newark and Secaucus. The federal share includes $766.5 million from a Federal Transit Administration grant agreement signed in January 2021.
Skanska's project page lists the job at $1,559,993,000, with NJ Transit as client and a 1,200-foot center span. The JV first won the contract in October 2021.
The numbers
Construction Dive's tally of materials is a good reminder of the scale:
- 45 million pounds of steel
- 219,000 cubic yards of concrete
- more than 35 miles of pipe piles and more than 3 miles of drilled shafts
- 4,850 linear feet of retaining walls
The standout piece of the job was the arches. The team assembled three 400-foot network-tied arches upstream at the Port of Coeymans, then floated each one roughly 30 hours down the Hudson and Hackensack rivers, under 18 bridges. Each arch has 60 cable hangers of 31 strands apiece. Skanska credits the prefab approach with a 50 percent cut in onsite steel erection time, and says bringing electricians and carpenters into the prefabrication work saved time and reduced hazards.
"Bringing the Portal North Bridge into full service is a significant milestone for the region" Laszlo Borhi, Project Executive, Skanska
The bigger picture
Northern New Jersey rail work isn't slowing down. Two days after Portal North went into full service, the Gateway Development Commission said the Hudson Tunnel Project's second tunnel boring machine had started mining from North Bergen. For contractors, finishing a job like this is as much about people as concrete. A team that has spent five years on marine foundations, heavy steel and live railroad staging is now rolling onto whatever comes next, and the next wave of corridor work will want exactly that experience.
What it means for hiring
- Our read: when a megaproject like this wraps up, project managers, structural steel supers and rail systems engineers with five years on one live corridor become some of the most sought-after people in the Northeast.
- The float-in approach is a niche skill set. Engineers who have planned heavy lifts, barge moves and marine logistics at this scale are rare, and bridge contractors bidding similar work will value them.
- Demolition of the old swing bridge in 2027 keeps a smaller crew busy, but most of the team's next moves will be decided over the coming months.
Building a team in Heavy Civil & Infrastructure?
Connor Goodall specialises in Heavy Civil & Infrastructure hiring at QP Group. Talk to Connor about the market, salaries or a search.
Sources
- NJ TRANSIT and Amtrak Mark Historic Milestone as Portal North Bridge Enters Full Service · Amtrak · 16 Nov 2026
- Skanska, Traylor Bros. JV wraps $1.6B New Jersey Transit project · Construction Dive · 18 Nov 2026
- GDC Launches Second Hudson Tunnel Project Tunnel Boring Machine · Gateway Development Commission · 18 Nov 2026
- Portal North Bridge (project page) · Skanska USA
Written by QP Group from the reporting and announcements above. Figures and quotes belong to the original sources.

More from The Civil Brief
- Granite closes two materials deals, adding Utah quarries and Tennessee asphalt plants22 Nov 2026
- AECOM's backlog hits a record $28B, and it says IIJA money is mostly unspent22 Nov 2026
- Both Hudson Tunnel tubes are now being bored through the Palisades22 Nov 2026
- Joseph B. Fay wins $38.6M job to clear the rest of Baltimore's Key Bridge22 Nov 2026