One in eight US contractors is doing data center work. That group is getting busier, and the other seven are not. Associated Builders and Contractors' Construction Backlog Indicator for October, released on 10 November, fell to 8.1 months. That is 0.6 months lower than September and 0.3 months lower than a year earlier.
Two markets in one number
The split inside the headline figure is the real story. Contractors with data center contracts saw backlog rise from 11.3 months to 11.5 months. The 88% of contractors without that work fell from 8.3 months to 7.6 months.
"This decline was largely due to worsening prospects for the 88% of contractors not under contract to work on data centers," Anirban Basu, chief economist, ABC
Construction Dive's report puts the gap between the two groups at nearly four months in October, up from three months in September. ABC adds that most of the contractors with data center work have more than $100 million in annual revenue.
The rest of the survey
- Commercial and institutional backlog fell to 8 months.
- Infrastructure dropped from 9.4 months to 8.7 months, its lowest since May 2025.
- Heavy industrial went the other way, rising to a 15-month high.
- Expectations for sales and staffing weakened, though all three of ABC's confidence readings stayed above 50, the line that signals expected growth over the next six months.
Profit margin expectations actually improved. Basu called that encouraging given recent increases in materials prices and borrowing costs, while noting that roughly 1 in 4 contractors still expect margins to shrink over the next six months.
The bigger picture
Last week's MEP Digest covered ABC's September spending data, which showed data center spending growing fast while total construction spending fell. October's backlog survey tells the same story from the contractor's side. The work is there, but it is concentrated among larger firms with data center references.
That has a direct effect on MEP. Data centers are heavy on mechanical and electrical scope, so the contractors winning them are often the ones adding project teams, while firms focused on commercial or institutional work are watching their pipelines shorten. The survey also suggests staffing plans are cooling across the wider industry, which could make it a little easier for busy data center contractors to find experienced people.
What it means for hiring
- Backlog is concentrated in firms with data center contracts, and hiring demand tends to follow backlog. Expect those contractors to keep competing hard for MEP project managers, superintendents and commissioning leads.
- Weaker staffing expectations elsewhere could bring more experienced commercial and institutional MEP people into the market. That is an opportunity for growing teams that can retrain them on mission-critical work.
- For mid-size contractors, a first data center reference is becoming the thing that changes their backlog. People who have delivered one before are worth a premium in that context.
Building a team in MEP?
Tom Brennan specialises in MEP hiring at QP Group. Talk to Tom about the market, salaries or a search.
Sources
- ABC's Construction Backlog Indicator Drops in October · Associated Builders and Contractors · 10 Nov 2026
- Construction backlog growth streak snapped in October · Construction Dive · 10 Nov 2026
- Data centre spending is growing at a 217% annualised rate, and little else is · QP Insight · 9 Nov 2026
Written by QP Group from the reporting and announcements above. Figures and quotes belong to the original sources.

More from MEP Digest
- Promera buys Irish electrical contractor B&G Energy to wire hyperscale data centers22 Nov 2026
- Salas O'Brien leaves North America for the first time, merging with Australia's Aston Consulting22 Nov 2026
- Caltius backs Medford Wellington, a New England HVAC firm that was already buying22 Nov 2026
- IES Holdings ends fiscal 2026 with $4.96B of backlog and 4,000 new people from DBM Global22 Nov 2026